B24002006 KAPAPALA KOA CANOE MGNT AREA FENCE INSTALLATION, HAWAII ISLAND
- Solicitation Number
- B24002006version: 06
- Status
- Awarded
- Department
- Land & Natural Resources
- Division
- Forestry and Wildlife
- Islands (where the work/delivery is to be performed)
- Hawaii, Statewide
- Category
- Goods and Services
- Release Date
- 03/22/2024
- Amendment Date
- 04/17/2024
- Amendment Reason
- Updating Line Item #2 for clearing of fence line
- Offer Due Date & Time
- 04/17/2024 04:00 PM
- Description
- The State of Hawaii’s Division of Forestry and Wildlife (DOFAW) is seeking bids for replacing an existing fence, skirting, and pinning, or making it an ungulate-proof fence at the Kapapala Koa Canoe Management Area, as well as associated tasks such as clearing the fence corridor as needed. The successful bidder will enter a contract with the State of Hawaii, from which fence projects will be executed using a State of Hawaii Purchase Order (PO) or formal contract.
- Contact Person
- Omick, Jason
- jason.d.omick@hawaii.gov
- Phone
- 808-347-6869
- General Comments
- Procurement Officer
- DAVID SMITH
- Attachments
-
FY2024 Contract Kapapala Hawaii Island Fence Installation.pdf
Addendum 1.pdf
103D-1 General Conditions.pdf
Download All
Direct all questions regarding this Solicitation, and any questions or Issues relating to the accessibility of this Solicitation (Including the appendices and exhibits to this Document, and any other document related to this Solicitation), to: Omick, Jason.
B24002006 KAPAPALA KOA CANOE MGNT AREA FENCE INSTALLATION, HAWAII ISLAND
#
Title
Quantity
Unit of Measure
Commodity Code
Commodity Code | Description |
---|---|
238990 | Fence installation (except electronic containment fencing for pets) |
332323 | Fences and gates (except wire), metal, manufacturing |
- Quantity
- 1
- Unit of Measure
- EACH
- Title
- Mobilization Fee
- Description
- * Mobilization fee will be procured if needed only in the case of unforeseen circumstances arising due to the State changing the scope of the project. In the event of a change in the linear distances described above, the mobilization fee provided may be used to adjust the amounts to be paid.
Commodity Code | Description |
---|---|
238990 | Fence installation (except electronic containment fencing for pets) |
332323 | Fences and gates (except wire), metal, manufacturing |
- Quantity
- 34500
- Unit of Measure
- FOOT
- Title
- Clearing of the fence line
- Description
- Vegetation clearing will be done by hand or with small power tools only. The replacement of the Makai and NE fence lines shall be aligned using the existing fence line. Where vegetation clearing. or ground leveling is required, the corridor may be cleared no more than eight (8’) ft in width. All debris must be piled inside the fence at a minimum of eight (8’) ft from the fence line; debris must not impede foot or vehicular traffic along the fence line. Any holes resulting from removing rocks along the fenced corridor must be skirted, or the gap between the bottom strand of wire and the hole must be closed using a minimum of two anchors (see below). Ungulate proofing of the Mauka and SE fence line will require vegetation clearing of at least three (3’) ft and no more than six (6’) ft in width. Positioning of the corners and fence posts along the fence line will be at the Contractor’s discretion, although deviations of more than six (6’) ft of the fence line must be approved by DOFAW staff before any clearing of vegetation. Any clearing of trees greater than fifteen (15”) in diameter must be approved by DOFAW staff.
Commodity Code | Description |
---|---|
238990 | Fence installation (except electronic containment fencing for pets) |
332323 | Fences and gates (except wire), metal, manufacturing |
- Quantity
- 16500
- Unit of Measure
- FOOT
- Title
- Per ft cost (Makai and NE Fence line) – Full Replacement
- Description
- Per ft cost (Makai and NE Fence line) – Full Replacement
Commodity Code | Description |
---|---|
238990 | Fence installation (except electronic containment fencing for pets) |
332323 | Fences and gates (except wire), metal, manufacturing |
- Quantity
- 18000
- Unit of Measure
- FOOT
- Title
- Per ft cost (Mauka and SW Fenceline) - Fence skirting and pinnin
- Description
- Per ft cost (Mauka and SW Fenceline) - Fence skirting and
pinning
Commodity Code | Description |
---|---|
238990 | Fence installation (except electronic containment fencing for pets) |
332323 | Fences and gates (except wire), metal, manufacturing |
- Quantity
- 6
- Unit of Measure
- EACH
- Title
- Per gate cost
- Description
- Per gate cost
Commodity Code | Description |
---|---|
238990 | Fence installation (except electronic containment fencing for pets) |
332323 | Fences and gates (except wire), metal, manufacturing |
- Quantity
- 1
- Unit of Measure
- EACH
- Title
- Material Transportation from the Waimea base yard to the work ar
- Description
- Material Transportation from the Waimea base yard to the
work area
Direct all questions regarding this Solicitation, and any questions or Issues relating to the accessibility of this Solicitation (Including the appendices and exhibits to this Document, and any other document related to this Solicitation), to: Omick, Jason.