Public Display Award

General Information
Award Title
Repair Various Outdoor Lighting Fixtures – Capitol District
Award Description
Repair Various Outdoor Lighting Fixtures – Capitol District
Date of Notice of Award
08/08/2025
Solicitation Number
B26000034
Contract Number
CSD-26-001-O
Basis of Award
Price Analysis
Contract Start Date
08/13/2025
End Date / Delivery Date
06/06/2026
Awardee
C&C Electrical Contractor, Inc.
Method of Procurement
Competitive Sealed Bidding (IFB)
Department
Accounting and General Services
Original Award Amount
$120,000.00
Current Award Amount
$172,197.00
General Comments
Procurement of new custom pole to match existing will require additional time. Scope added during construction as a result of the discovery of an existing unstable pole requiring replacement.
Contact Person
Dixon Park
Email
dixon.j.park@hawaii.gov
Phone
808-831-6733
Line Items
Line Item Number
Line Item Title
Line Item Comments
Attachments
Code Table
Award By
Total Price
Quantity
Unit of Measure
LOT
Unit of Measure
LOT
Price per Unit
--
Total Price
$172,197.00
Title
Repair Various Outdoor Lighting Fixtures – Capitol District
Description
Removal and replacement of various exterior light poles and fixtures in the Capitol District.
Solicitation Attachment

Print
Amendments
Contract Original Start Date:
08/13/2025
Contract Original End Date / Delivery Date:
03/06/2026
Amendment Start Date:
08/13/2025
Amendment End Date / Delivery Date:
06/06/2026
Reason for Amendment:
Contract end date extended due to change order to add scope (additional pole to be replaced).
Original Award Amount:
$120,000.00
Amount of Amendment:
$.00
Total Amount Awarded:
$172,197.00
Contract Original Start Date:
08/13/2025
Contract Original End Date / Delivery Date:
03/06/2026
Reason for Amendment:
Incorporating two change requests; 1. Add'l work needed for pole foundations to ensure structural stability, 2. Add additional pole replacement to scope. Discovered add'l pole leaning and unstable.
Original Award Amount:
$120,000.00
Amount of Amendment:
$51,353.00
Total Amount Awarded:
$172,197.00
Contract Original Start Date:
08/13/2025
Contract Original End Date / Delivery Date:
12/03/2025
Amendment Start Date:
08/13/2025
Amendment End Date / Delivery Date:
03/06/2026
Reason for Amendment:
Specialized materials to match existing installation on order and not yet received.
Original Award Amount:
$120,000.00
Amount of Amendment:
$.00
Total Amount Awarded:
$120,844.00
Contract Original Start Date:
08/13/2025
Contract Original End Date / Delivery Date:
12/03/2025
Reason for Amendment:
Length of one pole to be replaced was observed at the project site by contractor to be longer than what was specified in the project plans. This results in a higher cost to replace. The difference in cost is $844; the total original awarded amount was $120,000.
Original Award Amount:
$120,000.00
Amount of Amendment:
$844.00
Total Amount Awarded:
$120,844.00
Instructions
  • TRANSACTION FEES: The awarded vendor shall pay a transaction fee of 0.75% (.0075) of the award, not to exceed $5,000 for each award. This transaction fee shall be based on the original award amount and the awarded vendor shall be responsible for payment of the fee to Tyler Hawaii, the vendor administering the HIePRO. Payment must be made to Tyler Hawaii within thirty (30) days of receipt of invoice. The invoice is generated based on the date the award is posted.
  • HAWAII GENERAL EXCISE TAX (GET): Unless otherwise stated in this solicitation, vendors shall include all applicable taxes in the price submitted. The Hawaii General Excise Tax (GET) shall not exceed 4.712% for the islands of Hawaii, Kauai, Oahu and Maui.
  • ADDITIONAL FEES AND CHARGES: Vendors shall include all applicable fees, charges, surcharges, shipping/handling, delivery, or any other charges associated with this solicitation in the price submitted.